RP - FDM

Objective:
To prototype Instrument cluster, Radiator grill, bonnet grill, ash trey assembly, glove box for a popular SUV.

Brief: Prototypes were required to validate the design before tooling. The prototypes were supplied to various tool rooms involved in the project.

Duration: 3 Weeks

Process: From the 3D UniGraphics file .stl files were obtained. Prototypes were built in various splits to accommodate in the build platform. They were later glued using a CynoAcculate glue & were supplied to a customer.

Result: RP helped the manufacturer avoid costly design mistakes especially in the tooling stage.